An excerpt from the German Federal Water Act ("WHG" §19) - Any work facilities dealing with materials that pose a potential threat to ground water i.e. storage, filling, production, treatment or use of any such products must be designed and equipped to avoid polluting water or have any other detrimental effect on its characteristics.
|
|
Construction Approval Our retention basins are manufactured in accordance with "StawaR" - the German technical requirements for retention basins made of steel. Any retention basin that deviates from these requirements is covered by one of our general construction approvals issued by the DIBt (German Institute for Technical Construction)
|
|
Retention Volume A retention basin must be able to retain the volume of the largest packaging unit or at least 10% of the total volume stored - whatever the greater. NB: in water protection areas the entire volume must retained i.e. 100%! |